Thursday, March 26, 2009

Perlis Power CCGT Plant

Perlis Power CCGT Plant

Perlis Power CCGT Plant II

Perlis Power CCGT Plant Under Contruction

More data Perlis Power CCGT Plant are as below:
  • Mechanical and Electrical Erection Works for a 675MW 3X KA 13E2 Perlis Combined Cycle Power Plant.

  • Mechanical and Electrical Erection Works for 675MW 3X KA 13E2 Gas Turbines, Steam Turbine, Balance of Plant and Piping for Perlis Combined Cycle Power Plant.
  • Construction started in Feb 2002 and ended in Nov 2002.
  • Client: Alstom Power Asia Pacific Sdn Bhd
  • Peak manpower: 800
Related Posts with Thumbnails